East Croydon MDU

The overall objective for the scheme was to undertake a feasibility study for Network Rail. Enable Design’s (formerly known as Equate Design) work involved multi-disciplinary surveys for the site, including PAS128 Surveys, and developing options to upgrade the existing Network Rail office accommodation in line with client requirements.

Key considerations for the optioneering works were:

  • Risk management
  • Budgetary constraints
  • Construction logistics
  • Operational logistics
  • Access
  • Environmental impact
  • Sustainability

The Team

  • Project Manager
  • Engineering Manager
  • Civil Engineer
  • Survey Engineer

  • Topographical survey
  • Ground Penetration Radar (GPR) survey
  • CCTV drainage survey
  • Ground investigation works – trial pits, windowless samples and contaminated ground / sample testing
  • Dilapidation survey
  • M&E and load monitoring surveys
  • UXO risk assessment
  • Condition assessment report for the existing office accommodation building
  • Feasibility report, with options for consideration by the client for the future design works

Gallery

Find out how we can help you

If we can help you in any way, please do get in touch. In order that we can assist you efficiently, please click on the link below. Alternatively, you can call us on 020 4566 9616.

Get in Touch